Bid Results

21st Century Library and Community Learning Center and Heritage Plaza Arboretum

06992 


 
Show Bid Items
Show Listed Subcontractors
  go

Engineer's Estimate 
   Total Amount: $46,501,540.00 * marks an allowance.
  Bid List Name   Bid List Total    
  Bid Items $46,501,540.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total  
  1 AREA 1: CONSTRUCTION OF LIBRARY BUILDING: ALL WORK DESCRIBED IN THE CONTRACT DOCUMENTS IN AREA 1 BUT NOT INCLUDED IN THE BID ITEMS BELOW. INCLUDES BUT NOT LIMITED TO ALL UTILITIES CONNECTIONS TO BUILDING EXTENDED FIVE(5) FEET FROM BUILDING PERIMETER; INC 1 LS $35,600,000.00   $35,600,000.00    
  2 AREA 2: CONSTRUCTION OF PLAZA: INCLUDES LANDSCAPING & IRRIGATION, CONCRETE PAVERS, PIP PERVIOUS CONCRETE, PERMEABLE CONCRETE PAVERS IN ALL OTHER AREAS INCLUDING AREA 1, AREA 3 & AREA 4); INCLUDES BUT NOT LIMITED TO RAINWATER CISTERN AND UTILITIES CONNECT 1 LS $5,685,000.00   $5,685,000.00    
  3 EXISTING LIBRARY BUILDING DEMOLITION, RECYCLING, SALVAGE AND DISPOSAL AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $215,000.00   $215,000.00    
  4 HAZARDOUS MATERIALS ABATEMENT AT EXISTING LIBRARY, AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $20,000.00   $20,000.00    
  5 AREA 3: MUNICIPAL GARAGE IMPROVEMENTS & INSTALLATIONS: INCLUDING BUT NOT LIMITED TO THE ELEVATOR, STAIRS AND UTILITIES, ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 3 BUT NOT INCLUDED IN BID ITEMS BELOW. LS COST TO EXCLUDE PHOTOVOLTAIC SYSTEM UNITS, 1 LS $850,000.00   $850,000.00    
  6 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A1: PER ELECTRICAL CONTRACT DOCUMENTS. 5 EA $100,000.00   $500,000.00    
  7 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $85,000.00   $85,000.00    
  8 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B1: PER ELECTRICAL CONTRACT DOCUMENTS. 4 EA $120,000.00   $480,000.00    
  9 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $65,000.00   $65,000.00    
  10 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B3: PER ELECTRICAL CONTRACT DOCUMENTS. 2 EA $60,000.00   $120,000.00    
  11 BUILDERS RISK INSURANCE 1 LS $150,000.00   $150,000.00    
  12 AREA 4: ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 4, INCLUDING BUT NOT LIMITED TO ELECTRICAL (E-SERIES), TELECOM (T-SERIES), SIGNAGE (SG-SERIES). LS COST TO EXCLUDE WORK DESCRIBED IN CIVIL DRAWINGS (C-SERIES) THAT ARE THAT ARE INCLUDE IN BID ITEMS 1 LS $1,200,000.00   $1,200,000.00    
  13 REMOVE EXISTING CURB/GUTTER 1100 LF $10.00   $11,000.00    
  14 CURB AND GUTTER 1000 LF $25.00   $25,000.00    
  15 REMOVE EXISTING SIDEWALK 16200 SF $3.00   $48,600.00    
  16 CONCRETE SIDEWALK 8400 SF $10.00   $84,000.00    
  17 VALLEY GUTTER 300 SF $15.00   $4,500.00    
  18 VEHICULAR PAVERS 460 SF $30.00   $13,800.00    
  19 DRIVEWAY 70 SF $12.00   $840.00    
  20 ASPHALT CONCRETE PAVING 390 TN $95.00   $37,050.00    
  21 PAVEMENT AGGREGATE BASE (CLASS II) 610 CY $20.00   $12,200.00    
  22 PEDESTRIAN CURB RAMPS 7 EA $2,500.00   $17,500.00    
  23 REMOVE EXISTING UTILITY 2100 LF $15.00   $31,500.00    
  24 1-1/2" WATER (PURPLE PVC SCHEDULE 40) 20 LF $20.00   $400.00    
  25 2" WATER (PURPLE PVC SCHEDULE 40) 10 LF $25.00   $250.00    
  26 2-1/2" WATER (PVC SCHEDULE 40) 170 LF $25.00   $4,250.00    
  27 2-1/2" WATER (PURPLE PVC SCHEDULE 40) 90 LF $30.00   $2,700.00    
  28 3" WATER (PURPLE PVC SCHEDULE 40) 290 LF $30.00   $8,700.00    
  29 3" WATER (PVC SCHEDULE 40) 50 LF $30.00   $1,500.00    
  30 6" WATER (PVC C900) 200 LF $50.00   $10,000.00    
  31 6" FIRE HYDRANT ASSEMBLY 2 EA $6,000.00   $12,000.00    
  32 2-1/2" REDUCED PRESSURE BACKFLOW ASSEMBLY 1 EA $3,500.00   $3,500.00    
  33 6" DOUBLE CHECK DETECTOR BACKFLOW ASSEMBLY 1 EA $8,000.00   $8,000.00    
  34 FIRE DEPARTMENT CONNECTION 1 EA $5,000.00   $5,000.00    
  35 4" SEWER (PVC - SDR 26) BY OPEN TRENCH 80 LF $80.00   $6,400.00    
  36 8" SEWER (PVC - SDR 26) BY OPEN TRENCH 400 LF $150.00   $60,000.00    
  37 SEWER CLEANOUT 2 EA $2,000.00   $4,000.00    
  38 SEWER MANHOLE 3 EA $5,000.00   $15,000.00    
  39 SEWER AREA DRAIN 1 EA $4,000.00   $4,000.00    
  40 CONNECT TO EXISTING SEWER LATERAL 1 EA $5,000.00   $5,000.00    
  41 CONNECT NEW 8" SEWER MAIN TO EXISTING SEWER MANHOLE 2 EA $6,000.00   $12,000.00    
  42 3" STORM DRAIN (PVC SDR 35) 150 LF $50.00   $7,500.00    
  43 4" PERFORATED STORM DRAIN (PVC SCHEDULE 40) 1250 EA $70.00   $87,500.00    
  44 6" STORM DRAIN (PVC SDR 35) 540 LF $100.00   $54,000.00    
  45 8" STORM DRAIN (PVC SDR 35) 20 LF $200.00   $4,000.00    
  46 8" STORM DRAIN FORCE MAIN (PVC C900) 10 LF $400.00   $4,000.00    
  47 12" STORM DRAIN (RCP CLASS III) 330 LF $120.00   $39,600.00    
  48 15" STORM DRAIN (RCP CLASS III) 800 LF $150.00   $120,000.00    
  49 STORM DRAIN SLOT DRAIN 50 LF $40.00   $2,000.00    
  50 STORM DRAIN TRENCH DRAIN 10 LF $50.00   $500.00    
  51 STORM DRAIN CLEANOUT 8 EA $1,000.00   $8,000.00    
  52 STORM DRAIN MANHOLE 8 EA $5,000.00   $40,000.00    
  53 STORM DRAIN FORCE MAIN JUNCTION BOX 1 EA $8,000.00   $8,000.00    
  54 STORM DRAIN LIFT STATION AND VALVE BOX 1 LS $50,000.00   $50,000.00    
  55 STORM DRAIN NUTRIENT SEPERATING BAFFLE BOX 1 EA $80,000.00   $80,000.00    
  56 STORM DRAIN AREA DRAIN 9 EA $1,000.00   $9,000.00    
  57 STORM DRAIN DROP INLET (12" X 12") 1 EA $2,000.00   $2,000.00    
  58 STORM DRAIN OVERFLOW DROP INLET (18" X 18") 1 EA $2,500.00   $2,500.00    
  59 STORM DRAIN CURB INLET (TYPE A) 4 EA $2,500.00   $10,000.00    
  60 STORM DRAIN CURB INLET (TYPE D) 1 EA $3,000.00   $3,000.00    
  61 15" BACKWATER VALVE 1 EA $5,000.00   $5,000.00    
  62 CONNECT TO EXISTING STORM DRAIN 1 EA $5,000.00   $5,000.00    
  63 EARTHWORK (EXCAVATION) 1400 CY $45.00   $63,000.00    
  64 1-1/2" CHECK VALVE 1 EA $250.00   $250.00    
  65 2" CHECK VALVE 1 EA $400.00   $400.00    
  66 2-1/2" GATE VALVE 1 EA $1,500.00   $1,500.00    
  67 6" GATE VALVE 3 EA $2,500.00   $7,500.00    
  68 ADJUST WATER VALVE TO GRADE 3 EA $500.00   $1,500.00    
  69 ADJUST GAS VALVE TO GRADE 2 EA $800.00   $1,600.00    
  70 ADJUST MONITORING WELL TO GRADE 3 EA $2,000.00   $6,000.00    
  71 SET STREET MONUMENT 2 EA $1,000.00   $2,000.00    
  72 ROADSIDE SIGNS 7 EA $300.00   $2,100.00    
  73 STRIPING 1 LS $50,000.00   $50,000.00    
  74 TRAFFIC SIGNAL MODIFICATIONS AT MISSION BLVD AND C STREET 1 LS $150,000.00   $150,000.00    
  75 TRAFFIC SIGNAL MODIFICATIONS AT C STREET AND WATKINS STREET 1 LS $120,000.00   $120,000.00    
  76 INSTALL BUS SHELTER 1 EA $5,000.00   $5,000.00    
  77 WATER POLLUTION CONTROL 1 LS $5,000.00   $5,000.00    
  78 CONTRACTOR TEMPORARY TRAFFIC CONTROL 1 LS $25,000.00   $25,000.00    
  79 CLEARING AND GRUBBING 1 LS $30,000.00   $30,000.00    
  80 SOIL PREP AND FINISH GRADING 35200 SF $2.00   $70,400.00    
 

General Contractor:  T.B. Penick & Sons, Inc.
15435 Innovation Drive Suite 100
San Diego, CA  92128 
  Bidder Status: Valid
 
Total Bid Amount:  $49,290,598.80 * marks an allowance.
  Bid List Name   Bid List Total    
  Bid Items $49,290,598.80  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 AREA 1: CONSTRUCTION OF LIBRARY BUILDING: ALL WORK DESCRIBED IN THE CONTRACT DOCUMENTS IN AREA 1 BUT NOT INCLUDED IN THE BID ITEMS BELOW. INCLUDES BUT NOT LIMITED TO ALL UTILITIES CONNECTIONS TO BUILDING EXTENDED FIVE(5) FEET FROM BUILDING PERIMETER; INC 1 LS $29,222,777.00   $29,222,777.00    
  2 AREA 2: CONSTRUCTION OF PLAZA: INCLUDES LANDSCAPING & IRRIGATION, CONCRETE PAVERS, PIP PERVIOUS CONCRETE, PERMEABLE CONCRETE PAVERS IN ALL OTHER AREAS INCLUDING AREA 1, AREA 3 & AREA 4); INCLUDES BUT NOT LIMITED TO RAINWATER CISTERN AND UTILITIES CONNECT 1 LS $8,542,042.00   $8,542,042.00    
  3 EXISTING LIBRARY BUILDING DEMOLITION, RECYCLING, SALVAGE AND DISPOSAL AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $188,800.00   $188,800.00    
  4 HAZARDOUS MATERIALS ABATEMENT AT EXISTING LIBRARY, AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $88,950.80   $88,950.80    
  5 AREA 3: MUNICIPAL GARAGE IMPROVEMENTS & INSTALLATIONS: INCLUDING BUT NOT LIMITED TO THE ELEVATOR, STAIRS AND UTILITIES, ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 3 BUT NOT INCLUDED IN BID ITEMS BELOW. LS COST TO EXCLUDE PHOTOVOLTAIC SYSTEM UNITS, 1 LS $3,596,649.00   $3,596,649.00    
  6 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A1: PER ELECTRICAL CONTRACT DOCUMENTS. 5 EA $116,711.40   $583,557.00    
  7 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $93,366.00   $93,366.00    
  8 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B1: PER ELECTRICAL CONTRACT DOCUMENTS. 4 EA $149,974.75   $599,899.00    
  9 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $133,309.00   $133,309.00    
  10 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B3: PER ELECTRICAL CONTRACT DOCUMENTS. 2 EA $133,323.00   $266,646.00    
  11 BUILDERS RISK INSURANCE 1 LS $233,895.00   $233,895.00    
  12 AREA 4: ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 4, INCLUDING BUT NOT LIMITED TO ELECTRICAL (E-SERIES), TELECOM (T-SERIES), SIGNAGE (SG-SERIES). LS COST TO EXCLUDE WORK DESCRIBED IN CIVIL DRAWINGS (C-SERIES) THAT ARE THAT ARE INCLUDE IN BID ITEMS 1 LS $3,596,649.00   $3,596,649.00    
  13 REMOVE EXISTING CURB/GUTTER 1,100 LF $8.50   $9,350.00    
  14 CURB AND GUTTER 1,000 LF $37.95   $37,950.00    
  15 REMOVE EXISTING SIDEWALK 16,200 SF $2.50   $40,500.00    
  16 CONCRETE SIDEWALK 8,400 SF $6.90   $57,960.00    
  17 VALLEY GUTTER 300 SF $40.25   $12,075.00    
  18 VEHICULAR PAVERS 460 SF $25.00   $11,500.00    
  19 DRIVEWAY 70 SF $17.25   $1,207.50    
  20 ASPHALT CONCRETE PAVING 390 TN $175.00   $68,250.00    
  21 PAVEMENT AGGREGATE BASE (CLASS II) 610 CY $78.00   $47,580.00    
  22 PEDESTRIAN CURB RAMPS 7 EA $632.50   $4,427.50    
  23 REMOVE EXISTING UTILITY 2,100 LF $3.00   $6,300.00    
  24 1-1/2" WATER (PURPLE PVC SCHEDULE 40) 20 LF $91.00   $1,820.00    
  25 2" WATER (PURPLE PVC SCHEDULE 40) 10 LF $95.00   $950.00    
  26 2-1/2" WATER (PVC SCHEDULE 40) 170 LF $101.00   $17,170.00    
  27 2-1/2" WATER (PURPLE PVC SCHEDULE 40) 90 LF $102.00   $9,180.00    
  28 3" WATER (PURPLE PVC SCHEDULE 40) 290 LF $110.00   $31,900.00    
  29 3" WATER (PVC SCHEDULE 40) 50 LF $108.00   $5,400.00    
  30 6" WATER (PVC C900) 200 LF $175.00   $35,000.00    
  31 6" FIRE HYDRANT ASSEMBLY 2 EA $742.00   $1,484.00    
  32 2-1/2" REDUCED PRESSURE BACKFLOW ASSEMBLY 1 EA $8,750.00   $8,750.00    
  33 6" DOUBLE CHECK DETECTOR BACKFLOW ASSEMBLY 1 EA $15,400.00   $15,400.00    
  34 FIRE DEPARTMENT CONNECTION 1 EA $3,500.00   $3,500.00    
  35 4" SEWER (PVC - SDR 26) BY OPEN TRENCH 80 LF $119.00   $9,520.00    
  36 8" SEWER (PVC - SDR 26) BY OPEN TRENCH 400 LF $133.00   $53,200.00    
  37 SEWER CLEANOUT 2 EA $1,050.00   $2,100.00    
  38 SEWER MANHOLE 3 EA $17,500.00   $52,500.00    
  39 SEWER AREA DRAIN 1 EA $1,750.00   $1,750.00    
  40 CONNECT TO EXISTING SEWER LATERAL 1 EA $2,450.00   $2,450.00    
  41 CONNECT NEW 8" SEWER MAIN TO EXISTING SEWER MANHOLE 2 EA $9,100.00   $18,200.00    
  42 3" STORM DRAIN (PVC SDR 35) 150 LF $119.00   $17,850.00    
  43 4" PERFORATED STORM DRAIN (PVC SCHEDULE 40) 1,250 EA $122.00   $152,500.00    
  44 6" STORM DRAIN (PVC SDR 35) 540 LF $129.00   $69,660.00    
  45 8" STORM DRAIN (PVC SDR 35) 20 LF $133.00   $2,660.00    
  46 8" STORM DRAIN FORCE MAIN (PVC C900) 10 LF $192.00   $1,920.00    
  47 12" STORM DRAIN (RCP CLASS III) 330 LF $214.00   $70,620.00    
  48 15" STORM DRAIN (RCP CLASS III) 800 LF $234.00   $187,200.00    
  49 STORM DRAIN SLOT DRAIN 50 LF $193.00   $9,650.00    
  50 STORM DRAIN TRENCH DRAIN 10 LF $332.00   $3,320.00    
  51 STORM DRAIN CLEANOUT 8 EA $1,050.00   $8,400.00    
  52 STORM DRAIN MANHOLE 8 EA $16,100.00   $128,800.00    
  53 STORM DRAIN FORCE MAIN JUNCTION BOX 1 EA $6,650.00   $6,650.00    
  54 STORM DRAIN LIFT STATION AND VALVE BOX 1 LS $88,900.00   $88,900.00    
  55 STORM DRAIN NUTRIENT SEPERATING BAFFLE BOX 1 EA $81,200.00   $81,200.00    
  56 STORM DRAIN AREA DRAIN 9 EA $1,750.00   $15,750.00    
  57 STORM DRAIN DROP INLET (12" X 12") 1 EA $3,150.00   $3,150.00    
  58 STORM DRAIN OVERFLOW DROP INLET (18" X 18") 1 EA $3,850.00   $3,850.00    
  59 STORM DRAIN CURB INLET (TYPE A) 4 EA $19,250.00   $77,000.00    
  60 STORM DRAIN CURB INLET (TYPE D) 1 EA $21,350.00   $21,350.00    
  61 15" BACKWATER VALVE 1 EA $23,800.00   $23,800.00    
  62 CONNECT TO EXISTING STORM DRAIN 1 EA $4,550.00   $4,550.00    
  63 EARTHWORK (EXCAVATION) 1,400 CY $160.00   $224,000.00    
  64 1-1/2" CHECK VALVE 1 EA $1,540.00   $1,540.00    
  65 2" CHECK VALVE 1 EA $1,750.00   $1,750.00    
  66 2-1/2" GATE VALVE 1 EA $1,330.00   $1,330.00    
  67 6" GATE VALVE 3 EA $3,500.00   $10,500.00    
  68 ADJUST WATER VALVE TO GRADE 3 EA $1,050.00   $3,150.00    
  69 ADJUST GAS VALVE TO GRADE 2 EA $840.00   $1,680.00    
  70 ADJUST MONITORING WELL TO GRADE 3 EA $1,190.00   $3,570.00    
  71 SET STREET MONUMENT 2 EA $1,900.00   $3,800.00    
  72 ROADSIDE SIGNS 7 EA $1,305.00   $9,135.00    
  73 STRIPING 1 LS $47,050.00   $47,050.00    
  74 TRAFFIC SIGNAL MODIFICATIONS AT MISSION BLVD AND C STREET 1 LS $100,000.00   $100,000.00    
  75 TRAFFIC SIGNAL MODIFICATIONS AT C STREET AND WATKINS STREET 1 LS $100,000.00   $100,000.00    
  76 INSTALL BUS SHELTER 1 EA $5,000.00   $5,000.00    
  77 WATER POLLUTION CONTROL 1 LS $3,500.00   $3,500.00    
  78 CONTRACTOR TEMPORARY TRAFFIC CONTROL 1 LS $7,500.00   $7,500.00    
  79 CLEARING AND GRUBBING 1 LS $48,000.00   $48,000.00    
  80 SOIL PREP AND FINISH GRADING 35,200 SF $0.75   $26,400.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Collins Electric
Stockton, CA 
PV - $2,400,000 Electrical- $4,600,000 Low Volt Sys- $1,000,000 $8,000,000.00 16.23% 115427 -   
  Ray L Hellwig Mechanical
Santa Clarita, CA 
HVAC $3,685,000.00 7.47% 616780 -   
  Triton Structural
San Diego, CA 
Concrete(Bldg)$3,200,000 Site Concrete $340,000 Misc metals $943,000 $3,540,000.00 7.18% 903428 -   
  Glazier Steel
Hayward, CA 
Structural Steel $3,100,000.00 6.28% 67;2835 -   
  Platinum Construction
Anaheim, CA 
Drywall & Metal Studs $2,895,000.00 5.87% 870864 -   
  United Builders/Lincoln Glass
San Jose, CA 
Glass & Glazing $2,010,000.00 4.07% 820333 -   
  Cleveland Marble
Orange, CA 
Terracotta Cladding $2,000,000.00 4.05% 856767 -   
  Ranbar
San Diego, CA 
Site Utilities $2,000,000.00 4.05% 844070 -   
  JR Stevens Company
Arcata, CA 
Millwork $1,570,000.00 3.18% 445547 -   
  Novum Structures
2 Union Square
Suite 210
Union City, CA  94587 
Specialty Glazed Structures $1,100,000.00 2.23% 888637 -   
  Gerdau Reinforcing Steel
San Diego, CA 
Rebar $900,000.00 1.82% 974202 -   
  Green Growth
Pleasanton, CA 
Landscape $815,000.00 1.65% 662718 -   
  European Paving Designs
San Jose, CA 
Interlocking Pavers $785,000.00 1.59% 445163 -   
  Paul's Plumbing
Oakland, CA 
Plumbing $582,000.00 1.18% 419974 -   
  Otis Elevator
North Highlands, CA 
Elevator $575,000.00 1.16% 7031 -   
  Antioch Paving
PO Box 1669
Antioch, CA  94509 
Earthwork $350,000 Site Demolition $50,000 $400,000.00 0.81% 129726 -   
  Ceiling Experts
Orangevale, CA 
Acoustical ceilings $385,000.00 0.78% 917629 -   
  Water-proofing Associates
975 Terra Bella Ave
Mountain View, CA  94043 
Roofing $330,000.00 0.66% 649862 -   
  Kim's Flooring
390 Swift Avenue
#21
South San Francisco, CA  94080 
Resilient Flooring $285,000.00 0.57% 739226 -   
  Project Contractor, Inc.
South San Francisco, CA 
Fire Sprinklers $225,000.00 0.45% 884221 -   
  TM Demolition
Richmond, CA 
Demo $180,000.00 0.36% 872202 -   
  J & R Thompson
Novato, CA 
Painting $170,000.00 0.34% 736414 -   
  E & S Masonry
Castro Valley, CA 
CMU $43,000.00 0.08% 562066 -   

General Contractor:  Alten Construction, Inc.
720 12th Street
Richmond, CA  94801 
  Bidder Status: Valid
 
Total Bid Amount:  $51,436,947.24 * marks an allowance.
  Bid List Name   Bid List Total    
  Bid Items $51,436,947.24  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 AREA 1: CONSTRUCTION OF LIBRARY BUILDING: ALL WORK DESCRIBED IN THE CONTRACT DOCUMENTS IN AREA 1 BUT NOT INCLUDED IN THE BID ITEMS BELOW. INCLUDES BUT NOT LIMITED TO ALL UTILITIES CONNECTIONS TO BUILDING EXTENDED FIVE(5) FEET FROM BUILDING PERIMETER; INC 1 LS $39,822,926.87   $39,822,926.87    
  2 AREA 2: CONSTRUCTION OF PLAZA: INCLUDES LANDSCAPING & IRRIGATION, CONCRETE PAVERS, PIP PERVIOUS CONCRETE, PERMEABLE CONCRETE PAVERS IN ALL OTHER AREAS INCLUDING AREA 1, AREA 3 & AREA 4); INCLUDES BUT NOT LIMITED TO RAINWATER CISTERN AND UTILITIES CONNECT 1 LS $5,234,783.06   $5,234,783.06    
  3 EXISTING LIBRARY BUILDING DEMOLITION, RECYCLING, SALVAGE AND DISPOSAL AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $415,350.00   $415,350.00    
  4 HAZARDOUS MATERIALS ABATEMENT AT EXISTING LIBRARY, AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $85,200.00   $85,200.00    
  5 AREA 3: MUNICIPAL GARAGE IMPROVEMENTS & INSTALLATIONS: INCLUDING BUT NOT LIMITED TO THE ELEVATOR, STAIRS AND UTILITIES, ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 3 BUT NOT INCLUDED IN BID ITEMS BELOW. LS COST TO EXCLUDE PHOTOVOLTAIC SYSTEM UNITS, 1 LS $993,168.31   $993,168.31    
  6 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A1: PER ELECTRICAL CONTRACT DOCUMENTS. 5 EA $124,297.22   $621,486.10    
  7 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $49,717.40   $49,717.40    
  8 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B1: PER ELECTRICAL CONTRACT DOCUMENTS. 4 EA $159,722.31   $638,889.24    
  9 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $141,974.09   $141,974.09    
  10 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B3: PER ELECTRICAL CONTRACT DOCUMENTS. 2 EA $70,993.97   $141,987.94    
  11 BUILDERS RISK INSURANCE 1 LS $97,980.00   $97,980.00    
  12 AREA 4: ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 4, INCLUDING BUT NOT LIMITED TO ELECTRICAL (E-SERIES), TELECOM (T-SERIES), SIGNAGE (SG-SERIES). LS COST TO EXCLUDE WORK DESCRIBED IN CIVIL DRAWINGS (C-SERIES) THAT ARE THAT ARE INCLUDE IN BID ITEMS 1 LS $1,436,488.91   $1,436,488.91    
  13 REMOVE EXISTING CURB/GUTTER 1,100 LF $13.85   $15,235.00    
  14 CURB AND GUTTER 1,000 LF $37.28   $37,280.00    
  15 REMOVE EXISTING SIDEWALK 16,200 SF $0.80   $12,960.00    
  16 CONCRETE SIDEWALK 8,400 SF $10.12   $85,008.00    
  17 VALLEY GUTTER 300 SF $13.85   $4,155.00    
  18 VEHICULAR PAVERS 460 SF $58.09   $26,721.40    
  19 DRIVEWAY 70 SF $17.04   $1,192.80    
  20 ASPHALT CONCRETE PAVING 390 TN $127.80   $49,842.00    
  21 PAVEMENT AGGREGATE BASE (CLASS II) 610 CY $70.29   $42,876.90    
  22 PEDESTRIAN CURB RAMPS 7 EA $3,356.36   $23,494.52    
  23 REMOVE EXISTING UTILITY 2,100 LF $37.28   $78,288.00    
  24 1-1/2" WATER (PURPLE PVC SCHEDULE 40) 20 LF $62.84   $1,256.80    
  25 2" WATER (PURPLE PVC SCHEDULE 40) 10 LF $63.37   $633.70    
  26 2-1/2" WATER (PVC SCHEDULE 40) 170 LF $42.60   $7,242.00    
  27 2-1/2" WATER (PURPLE PVC SCHEDULE 40) 90 LF $61.77   $5,559.30    
  28 3" WATER (PURPLE PVC SCHEDULE 40) 290 LF $60.71   $17,605.90    
  29 3" WATER (PVC SCHEDULE 40) 50 LF $60.71   $3,035.50    
  30 6" WATER (PVC C900) 200 LF $111.83   $22,366.00    
  31 6" FIRE HYDRANT ASSEMBLY 2 EA $12,780.00   $25,560.00    
  32 2-1/2" REDUCED PRESSURE BACKFLOW ASSEMBLY 1 EA $7,130.00   $7,130.00    
  33 6" DOUBLE CHECK DETECTOR BACKFLOW ASSEMBLY 1 EA $24,495.00   $24,495.00    
  34 FIRE DEPARTMENT CONNECTION 1 EA $8,520.00   $8,520.00    
  35 4" SEWER (PVC - SDR 26) BY OPEN TRENCH 80 LF $85.20   $6,816.00    
  36 8" SEWER (PVC - SDR 26) BY OPEN TRENCH 400 LF $118.22   $47,288.00    
  37 SEWER CLEANOUT 2 EA $2,236.50   $4,473.00    
  38 SEWER MANHOLE 3 EA $9,148.35   $27,445.05    
  39 SEWER AREA DRAIN 1 EA $2,705.10   $2,705.10    
  40 CONNECT TO EXISTING SEWER LATERAL 1 EA $5,005.50   $5,005.50    
  41 CONNECT NEW 8" SEWER MAIN TO EXISTING SEWER MANHOLE 2 EA $5,630.66   $11,261.32    
  42 3" STORM DRAIN (PVC SDR 35) 150 LF $55.38   $8,307.00    
  43 4" PERFORATED STORM DRAIN (PVC SCHEDULE 40) 1,250 EA $41.54   $51,925.00    
  44 6" STORM DRAIN (PVC SDR 35) 540 LF $58.58   $31,633.20    
  45 8" STORM DRAIN (PVC SDR 35) 20 LF $85.20   $1,704.00    
  46 8" STORM DRAIN FORCE MAIN (PVC C900) 10 LF $256.87   $2,568.70    
  47 12" STORM DRAIN (RCP CLASS III) 330 LF $129.93   $42,876.90    
  48 15" STORM DRAIN (RCP CLASS III) 800 LF $133.13   $106,504.00    
  49 STORM DRAIN SLOT DRAIN 50 LF $84.14   $4,207.00    
  50 STORM DRAIN TRENCH DRAIN 10 LF $287.55   $2,875.50    
  51 STORM DRAIN CLEANOUT 8 EA $814.73   $6,517.84    
  52 STORM DRAIN MANHOLE 8 EA $7,231.35   $57,850.80    
  53 STORM DRAIN FORCE MAIN JUNCTION BOX 1 EA $9,052.50   $9,052.50    
  54 STORM DRAIN LIFT STATION AND VALVE BOX 1 LS $37,988.55   $37,988.55    
  55 STORM DRAIN NUTRIENT SEPERATING BAFFLE BOX 1 EA $46,327.50   $46,327.50    
  56 STORM DRAIN AREA DRAIN 9 EA $4,153.50   $37,381.50    
  57 STORM DRAIN DROP INLET (12" X 12") 1 EA $42,054.68   $42,054.68    
  58 STORM DRAIN OVERFLOW DROP INLET (18" X 18") 1 EA $8,466.75   $8,466.75    
  59 STORM DRAIN CURB INLET (TYPE A) 4 EA $3,674.25   $14,697.00    
  60 STORM DRAIN CURB INLET (TYPE D) 1 EA $5,995.95   $5,995.95    
  61 15" BACKWATER VALVE 1 EA $12,886.50   $12,886.50    
  62 CONNECT TO EXISTING STORM DRAIN 1 EA $7,758.53   $7,758.53    
  63 EARTHWORK (EXCAVATION) 1,400 CY $73.49   $102,886.00    
  64 1-1/2" CHECK VALVE 1 EA $628.35   $628.35    
  65 2" CHECK VALVE 1 EA $661.37   $661.37    
  66 2-1/2" GATE VALVE 1 EA $696.51   $696.51    
  67 6" GATE VALVE 3 EA $2,843.55   $8,530.65    
  68 ADJUST WATER VALVE TO GRADE 3 EA $639.00   $1,917.00    
  69 ADJUST GAS VALVE TO GRADE 2 EA $639.00   $1,278.00    
  70 ADJUST MONITORING WELL TO GRADE 3 EA $1,065.00   $3,195.00    
  71 SET STREET MONUMENT 2 EA $1,491.00   $2,982.00    
  72 ROADSIDE SIGNS 7 EA $426.00   $2,982.00    
  73 STRIPING 1 LS $20,128.50   $20,128.50    
  74 TRAFFIC SIGNAL MODIFICATIONS AT MISSION BLVD AND C STREET 1 LS $99,045.00   $99,045.00    
  75 TRAFFIC SIGNAL MODIFICATIONS AT C STREET AND WATKINS STREET 1 LS $137,385.00   $137,385.00    
  76 INSTALL BUS SHELTER 1 EA $21,300.00   $21,300.00    
  77 WATER POLLUTION CONTROL 1 LS $78,543.75   $78,543.75    
  78 CONTRACTOR TEMPORARY TRAFFIC CONTROL 1 LS $30,885.00   $30,885.00    
  79 CLEARING AND GRUBBING 1 LS $42,600.00   $42,600.00    
  80 SOIL PREP AND FINISH GRADING 35,200 SF $1.60   $56,320.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Collins Electric
Stockton, CA 
Electrical & PV $8,053,598.00 15.65% 115427 -   
  Kwan Wo Ironworks
1383 Armstrong Ave
San Francisco, CA  94124 
Structural Steel $4,113,000.00 7.99% 643621 -   
  Bay Cities
Richmond, CA 
HVAC $4,100,000.00 7.97% 645126 -   
  AHC Glass
31054 San Antonio Street
Hayward, CA  94544 
metal railings & windows & glazing $2,312,500.00 4.49% 820416 -   
  Best Contracting Services, Inc.
19027 South Hamilton Avenue
Gardena, CA  90248 
Alum. & Terra Cotta panels & sheet metal $2,103,100.00 4.08% 456263 -   
  Ceiling Experts
Orangevale, CA 
Acoustical panel ceilings $2,000,000.00 3.88% 917629 -   
  Peck and Hiller Company
870 Napa Corp Way
Napa, CA  94558 
concrete forming $1,915,000.00 3.72% 109795 -   
  Ghilotti Bros., Inc
525 Jacoby St
San Rafael, CA  94901 
Grading / Paving $1,505,480.00 2.92% 132128 -   
  Rebar International
2880 Zanker Road
Milpitas, CA  95035 
Rebar $1,161,950.00 2.25% 983536 -   
  Marina Landscape, Inc.
1900 South Lewis Street
Anaheim, CA  92805 
Landscaping $995,712.00 1.93% 492862 -   
  WoodCraft Company
6700 GateWay Park Dr
Suite #4
San Diego, CA  92154 
Woodwork $974,724.00 1.89% 940315 -   
  BCI
1200 Sixth Street
Berkeley, CA  94710 
site & pervious concrete $842,990.00 1.63% 290755 -   
  European Paving Designs
San Jose, CA 
Pavers $836,664.00 1.62% 445163 -   
  Paul's Plumbing
Oakland, CA 
Plumbing $599,650.00 1.16% 419974 -   
  Otis Elevator
North Highlands, CA 
electric traction elevator $587,400.00 1.14% 7031 -   
  Visible Graphics
21520 Strathem St.
Canoga Park, CA  91304 
Signage $448,287.00 0.87% 745555 -   
  CAMPANELLA CORPORATION
HAYWARD, CA 
Demolition $390,000.00 0.75% 750648 -   
  Linden Steel & Construction
Manteca, CA 
Metal Deck $358,000.00 0.69% 846699 -   
  Water-proofing Associates
975 Terra Bella Ave
Mountain View, CA  94043 
single ply roofing $338,499.00 0.65% 649862 -   
  Wolverine Fire Protection Co.
2170 Commerce Ave.
Concord, CA  94520 
Fire Suppression Sprinklers $338,000.00 0.65% 896977 -   
  Kim's Flooring
390 Swift Avenue
#21
South San Francisco, CA  94080 
resilient flooring $292,000.00 0.56% 739226 -   
  Danco
3142 Diablo Ave
Hayward, CA  94545 
Waterproofing $234,000.00 0.45% 350190 -   
  Ranbar
San Diego, CA 
 -   

General Contractor:  USS Cal Builders, Inc.
8051 Main Street
Stanton, CA  90680 
  Bidder Status: Valid
 
Total Bid Amount:  $57,162,530.00 * marks an allowance.
  Bid List Name   Bid List Total    
  Bid Items $57,162,530.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 AREA 1: CONSTRUCTION OF LIBRARY BUILDING: ALL WORK DESCRIBED IN THE CONTRACT DOCUMENTS IN AREA 1 BUT NOT INCLUDED IN THE BID ITEMS BELOW. INCLUDES BUT NOT LIMITED TO ALL UTILITIES CONNECTIONS TO BUILDING EXTENDED FIVE(5) FEET FROM BUILDING PERIMETER; INC 1 LS $46,000,000.00   $46,000,000.00    
  2 AREA 2: CONSTRUCTION OF PLAZA: INCLUDES LANDSCAPING & IRRIGATION, CONCRETE PAVERS, PIP PERVIOUS CONCRETE, PERMEABLE CONCRETE PAVERS IN ALL OTHER AREAS INCLUDING AREA 1, AREA 3 & AREA 4); INCLUDES BUT NOT LIMITED TO RAINWATER CISTERN AND UTILITIES CONNECT 1 LS $4,500,000.00   $4,500,000.00    
  3 EXISTING LIBRARY BUILDING DEMOLITION, RECYCLING, SALVAGE AND DISPOSAL AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $600,000.00   $600,000.00    
  4 HAZARDOUS MATERIALS ABATEMENT AT EXISTING LIBRARY, AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $100,000.00   $100,000.00    
  5 AREA 3: MUNICIPAL GARAGE IMPROVEMENTS & INSTALLATIONS: INCLUDING BUT NOT LIMITED TO THE ELEVATOR, STAIRS AND UTILITIES, ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 3 BUT NOT INCLUDED IN BID ITEMS BELOW. LS COST TO EXCLUDE PHOTOVOLTAIC SYSTEM UNITS, 1 LS $800,000.00   $800,000.00    
  6 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A1: PER ELECTRICAL CONTRACT DOCUMENTS. 5 EA $135,000.00   $675,000.00    
  7 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $105,000.00   $105,000.00    
  8 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B1: PER ELECTRICAL CONTRACT DOCUMENTS. 4 EA $165,000.00   $660,000.00    
  9 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $165,000.00   $165,000.00    
  10 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B3: PER ELECTRICAL CONTRACT DOCUMENTS. 2 EA $165,000.00   $330,000.00    
  11 BUILDERS RISK INSURANCE 1 LS $528,000.00   $528,000.00    
  12 AREA 4: ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 4, INCLUDING BUT NOT LIMITED TO ELECTRICAL (E-SERIES), TELECOM (T-SERIES), SIGNAGE (SG-SERIES). LS COST TO EXCLUDE WORK DESCRIBED IN CIVIL DRAWINGS (C-SERIES) THAT ARE THAT ARE INCLUDE IN BID ITEMS 1 LS $200,000.00   $200,000.00    
  13 REMOVE EXISTING CURB/GUTTER 1,100 LF $17.60   $19,360.00    
  14 CURB AND GUTTER 1,000 LF $48.00   $48,000.00    
  15 REMOVE EXISTING SIDEWALK 16,200 SF $2.20   $35,640.00    
  16 CONCRETE SIDEWALK 8,400 SF $7.80   $65,520.00    
  17 VALLEY GUTTER 300 SF $38.50   $11,550.00    
  18 VEHICULAR PAVERS 460 SF $44.00   $20,240.00    
  19 DRIVEWAY 70 SF $55.00   $3,850.00    
  20 ASPHALT CONCRETE PAVING 390 TN $220.00   $85,800.00    
  21 PAVEMENT AGGREGATE BASE (CLASS II) 610 CY $110.00   $67,100.00    
  22 PEDESTRIAN CURB RAMPS 7 EA $3,850.00   $26,950.00    
  23 REMOVE EXISTING UTILITY 2,100 LF $55.00   $115,500.00    
  24 1-1/2" WATER (PURPLE PVC SCHEDULE 40) 20 LF $44.00   $880.00    
  25 2" WATER (PURPLE PVC SCHEDULE 40) 10 LF $50.00   $500.00    
  26 2-1/2" WATER (PVC SCHEDULE 40) 170 LF $55.00   $9,350.00    
  27 2-1/2" WATER (PURPLE PVC SCHEDULE 40) 90 LF $38.50   $3,465.00    
  28 3" WATER (PURPLE PVC SCHEDULE 40) 290 LF $41.00   $11,890.00    
  29 3" WATER (PVC SCHEDULE 40) 50 LF $46.20   $2,310.00    
  30 6" WATER (PVC C900) 200 LF $82.00   $16,400.00    
  31 6" FIRE HYDRANT ASSEMBLY 2 EA $9,400.00   $18,800.00    
  32 2-1/2" REDUCED PRESSURE BACKFLOW ASSEMBLY 1 EA $2,400.00   $2,400.00    
  33 6" DOUBLE CHECK DETECTOR BACKFLOW ASSEMBLY 1 EA $8,600.00   $8,600.00    
  34 FIRE DEPARTMENT CONNECTION 1 EA $2,300.00   $2,300.00    
  35 4" SEWER (PVC - SDR 26) BY OPEN TRENCH 80 LF $50.00   $4,000.00    
  36 8" SEWER (PVC - SDR 26) BY OPEN TRENCH 400 LF $66.00   $26,400.00    
  37 SEWER CLEANOUT 2 EA $1,300.00   $2,600.00    
  38 SEWER MANHOLE 3 EA $10,560.00   $31,680.00    
  39 SEWER AREA DRAIN 1 EA $1,300.00   $1,300.00    
  40 CONNECT TO EXISTING SEWER LATERAL 1 EA $11,500.00   $11,500.00    
  41 CONNECT NEW 8" SEWER MAIN TO EXISTING SEWER MANHOLE 2 EA $31,900.00   $63,800.00    
  42 3" STORM DRAIN (PVC SDR 35) 150 LF $38.50   $5,775.00    
  43 4" PERFORATED STORM DRAIN (PVC SCHEDULE 40) 1,250 EA $21.00   $26,250.00    
  44 6" STORM DRAIN (PVC SDR 35) 540 LF $63.00   $34,020.00    
  45 8" STORM DRAIN (PVC SDR 35) 20 LF $7.50   $150.00    
  46 8" STORM DRAIN FORCE MAIN (PVC C900) 10 LF $99.00   $990.00    
  47 12" STORM DRAIN (RCP CLASS III) 330 LF $132.00   $43,560.00    
  48 15" STORM DRAIN (RCP CLASS III) 800 LF $132.00   $105,600.00    
  49 STORM DRAIN SLOT DRAIN 50 LF $132.00   $6,600.00    
  50 STORM DRAIN TRENCH DRAIN 10 LF $132.00   $1,320.00    
  51 STORM DRAIN CLEANOUT 8 EA $1,300.00   $10,400.00    
  52 STORM DRAIN MANHOLE 8 EA $10,800.00   $86,400.00    
  53 STORM DRAIN FORCE MAIN JUNCTION BOX 1 EA $9,000.00   $9,000.00    
  54 STORM DRAIN LIFT STATION AND VALVE BOX 1 LS $12,800.00   $12,800.00    
  55 STORM DRAIN NUTRIENT SEPERATING BAFFLE BOX 1 EA $8,600.00   $8,600.00    
  56 STORM DRAIN AREA DRAIN 9 EA $715.00   $6,435.00    
  57 STORM DRAIN DROP INLET (12" X 12") 1 EA $2,000.00   $2,000.00    
  58 STORM DRAIN OVERFLOW DROP INLET (18" X 18") 1 EA $2,600.00   $2,600.00    
  59 STORM DRAIN CURB INLET (TYPE A) 4 EA $7,200.00   $28,800.00    
  60 STORM DRAIN CURB INLET (TYPE D) 1 EA $8,600.00   $8,600.00    
  61 15" BACKWATER VALVE 1 EA $7,500.00   $7,500.00    
  62 CONNECT TO EXISTING STORM DRAIN 1 EA $9,600.00   $9,600.00    
  63 EARTHWORK (EXCAVATION) 1,400 CY $88.00   $123,200.00    
  64 1-1/2" CHECK VALVE 1 EA $560.00   $560.00    
  65 2" CHECK VALVE 1 EA $705.00   $705.00    
  66 2-1/2" GATE VALVE 1 EA $780.00   $780.00    
  67 6" GATE VALVE 3 EA $2,200.00   $6,600.00    
  68 ADJUST WATER VALVE TO GRADE 3 EA $1,320.00   $3,960.00    
  69 ADJUST GAS VALVE TO GRADE 2 EA $1,320.00   $2,640.00    
  70 ADJUST MONITORING WELL TO GRADE 3 EA $3,400.00   $10,200.00    
  71 SET STREET MONUMENT 2 EA $5,500.00   $11,000.00    
  72 ROADSIDE SIGNS 7 EA $550.00   $3,850.00    
  73 STRIPING 1 LS $33,000.00   $33,000.00    
  74 TRAFFIC SIGNAL MODIFICATIONS AT MISSION BLVD AND C STREET 1 LS $75,000.00   $75,000.00    
  75 TRAFFIC SIGNAL MODIFICATIONS AT C STREET AND WATKINS STREET 1 LS $275,000.00   $275,000.00    
  76 INSTALL BUS SHELTER 1 EA $30,000.00   $30,000.00    
  77 WATER POLLUTION CONTROL 1 LS $99,000.00   $99,000.00    
  78 CONTRACTOR TEMPORARY TRAFFIC CONTROL 1 LS $330,000.00   $330,000.00    
  79 CLEARING AND GRUBBING 1 LS $262,550.00   $262,550.00    
  80 SOIL PREP AND FINISH GRADING 35,200 SF $2.75   $96,800.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Collins Electric
Stockton, CA 
Electrical $6,500,000.00 11.37% 115427 -   
  CLS Constructors
21935 Van Buren st Unit B-7
Grand Terrace, CA  92313 
Site & Bldg Concrete (Partial) $4,646,980.00 8.12% 980071 -   
  Platinum Construction
Anaheim, CA 
Framing, drywall & Plaster $3,100,000.00 5.42% 890664 -   
  Best Contracting Services, Inc.
19027 South Hamilton Avenue
Gardena, CA  90248 
Roofing (Partial), Sheet Metal & Terracotta $2,704,600.00 4.73% 456263 -   
  Ceiling Experts
Orangevale, CA 
Acoustical Ceiling (Partial) $2,000,000.00 3.49% 917629 -   
  Stanton Utilities
Stanton, CA  90680 
Site Utilities, Plumbing (Partial) $1,580,000.00 2.76% 967030 -   
  Novum Structures
2 Union Square
Suite 210
Union City, CA  94587 
Structures Glazing (Partial) $1,150,000.00 2.01% 888817 -   
  WoodCraft Company
6700 GateWay Park Dr
Suite #4
San Diego, CA  92154 
Rough Carpentry, Millwork (Partial) $945,202.00 1.65% 940315 -   
  JMW Carpet & Flooring
South San Francisco, CA 
Flooring (Partial) $878,000.00 1.53% 992965 -   
  Eagle Contracting Inc
7331 Shelby Pl Rancho Cucamonga CA 91739
Rancho Cucamonga, CA  91739 
Demo & Abatement (Partial) $580,000.00 1.01% 970089 -   
  PCD
1032 Maxwell Drive
Santa Rosa, CA  95401 
AV Systems (Partial) $420,398.00 0.73% 527657 -   
  Project Contractor, Inc.
South San Francisco, CA 
Fire Sprinkler (Partial) $237,500.00 0.41% 889221 -   
  Freas Plastering
2680 Cloverdale Avenue
Concord, CA  94518 
Fireproofing (Partial) $180,200.00 0.31% 602914 -   
  Crusader Fence Company
3115 GOLD VALLEY DRIVE
RANCHO CORDOVA, CA  95742 
Fencing (Partial) $169,500.00 0.29% 726527 -   
  R-Bros Painting
San Jose, CA 
Waterproofing (Partial) $142,363.00 0.24% 472978 -   
  Ross McDonald
1154 Stealth St
Livermore, CA  94551 
Mobile Storage System $38,970.00 0.06% 314333 -   

General Contractor:  Roebbelen Contracting, Inc.
1241 Hawks Flight Court
El Dorado Hills, CA  95762 
  Bidder Status: Valid
 
Total Bid Amount:  $58,601,750.00 * marks an allowance.
  Bid List Name   Bid List Total    
  Bid Items $58,601,750.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 AREA 1: CONSTRUCTION OF LIBRARY BUILDING: ALL WORK DESCRIBED IN THE CONTRACT DOCUMENTS IN AREA 1 BUT NOT INCLUDED IN THE BID ITEMS BELOW. INCLUDES BUT NOT LIMITED TO ALL UTILITIES CONNECTIONS TO BUILDING EXTENDED FIVE(5) FEET FROM BUILDING PERIMETER; INC 1 LS $45,300,000.00   $45,300,000.00    
  2 AREA 2: CONSTRUCTION OF PLAZA: INCLUDES LANDSCAPING & IRRIGATION, CONCRETE PAVERS, PIP PERVIOUS CONCRETE, PERMEABLE CONCRETE PAVERS IN ALL OTHER AREAS INCLUDING AREA 1, AREA 3 & AREA 4); INCLUDES BUT NOT LIMITED TO RAINWATER CISTERN AND UTILITIES CONNECT 1 LS $5,100,000.00   $5,100,000.00    
  3 EXISTING LIBRARY BUILDING DEMOLITION, RECYCLING, SALVAGE AND DISPOSAL AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $756,772.00   $756,772.00    
  4 HAZARDOUS MATERIALS ABATEMENT AT EXISTING LIBRARY, AS DESCRIBED IN CONTRACT DOCUMENTS. 1 LS $91,242.00   $91,242.00    
  5 AREA 3: MUNICIPAL GARAGE IMPROVEMENTS & INSTALLATIONS: INCLUDING BUT NOT LIMITED TO THE ELEVATOR, STAIRS AND UTILITIES, ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 3 BUT NOT INCLUDED IN BID ITEMS BELOW. LS COST TO EXCLUDE PHOTOVOLTAIC SYSTEM UNITS, 1 LS $1,160,000.00   $1,160,000.00    
  6 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A1: PER ELECTRICAL CONTRACT DOCUMENTS. 5 EA $254,000.00   $1,270,000.00    
  7 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE A2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $261,000.00   $261,000.00    
  8 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B1: PER ELECTRICAL CONTRACT DOCUMENTS. 4 EA $322,000.00   $1,288,000.00    
  9 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B2: PER ELECTRICAL CONTRACT DOCUMENTS. 1 EA $304,100.00   $304,100.00    
  10 MUNICIPAL GARAGE PHOTOTVOLTAIC SYSTEM: PANEL SYSTEM TYPE B3: PER ELECTRICAL CONTRACT DOCUMENTS. 2 EA $152,000.00   $304,000.00    
  11 BUILDERS RISK INSURANCE 1 LS $284,461.00   $284,461.00    
  12 AREA 4: ALL WORK DESCRIBED IN CONTRACT DOCUMENTS IN AREA 4, INCLUDING BUT NOT LIMITED TO ELECTRICAL (E-SERIES), TELECOM (T-SERIES), SIGNAGE (SG-SERIES). LS COST TO EXCLUDE WORK DESCRIBED IN CIVIL DRAWINGS (C-SERIES) THAT ARE THAT ARE INCLUDE IN BID ITEMS 1 LS $318,000.00   $318,000.00    
  13 REMOVE EXISTING CURB/GUTTER 1,100 LF $15.00   $16,500.00    
  14 CURB AND GUTTER 1,000 LF $38.80   $38,800.00    
  15 REMOVE EXISTING SIDEWALK 16,200 SF $2.00   $32,400.00    
  16 CONCRETE SIDEWALK 8,400 SF $14.40   $120,960.00    
  17 VALLEY GUTTER 300 SF $18.00   $5,400.00    
  18 VEHICULAR PAVERS 460 SF $20.00   $9,200.00    
  19 DRIVEWAY 70 SF $28.00   $1,960.00    
  20 ASPHALT CONCRETE PAVING 390 TN $214.70   $83,733.00    
  21 PAVEMENT AGGREGATE BASE (CLASS II) 610 CY $37.60   $22,936.00    
  22 PEDESTRIAN CURB RAMPS 7 EA $2,194.00   $15,358.00    
  23 REMOVE EXISTING UTILITY 2,100 LF $38.11   $80,031.00    
  24 1-1/2" WATER (PURPLE PVC SCHEDULE 40) 20 LF $64.40   $1,288.00    
  25 2" WATER (PURPLE PVC SCHEDULE 40) 10 LF $69.70   $697.00    
  26 2-1/2" WATER (PVC SCHEDULE 40) 170 LF $48.30   $8,211.00    
  27 2-1/2" WATER (PURPLE PVC SCHEDULE 40) 90 LF $54.00   $4,860.00    
  28 3" WATER (PURPLE PVC SCHEDULE 40) 290 LF $51.00   $14,790.00    
  29 3" WATER (PVC SCHEDULE 40) 50 LF $54.00   $2,700.00    
  30 6" WATER (PVC C900) 200 LF $86.00   $17,200.00    
  31 6" FIRE HYDRANT ASSEMBLY 2 EA $4,831.00   $9,662.00    
  32 2-1/2" REDUCED PRESSURE BACKFLOW ASSEMBLY 1 EA $4,830.00   $4,830.00    
  33 6" DOUBLE CHECK DETECTOR BACKFLOW ASSEMBLY 1 EA $8,587.00   $8,587.00    
  34 FIRE DEPARTMENT CONNECTION 1 EA $3,757.00   $3,757.00    
  35 4" SEWER (PVC - SDR 26) BY OPEN TRENCH 80 LF $86.00   $6,880.00    
  36 8" SEWER (PVC - SDR 26) BY OPEN TRENCH 400 LF $150.00   $60,000.00    
  37 SEWER CLEANOUT 2 EA $644.00   $1,288.00    
  38 SEWER MANHOLE 3 EA $7,520.00   $22,560.00    
  39 SEWER AREA DRAIN 1 EA $2,150.00   $2,150.00    
  40 CONNECT TO EXISTING SEWER LATERAL 1 EA $650.00   $650.00    
  41 CONNECT NEW 8" SEWER MAIN TO EXISTING SEWER MANHOLE 2 EA $610.00   $1,220.00    
  42 3" STORM DRAIN (PVC SDR 35) 150 LF $32.20   $4,830.00    
  43 4" PERFORATED STORM DRAIN (PVC SCHEDULE 40) 1,250 EA $32.20   $40,250.00    
  44 6" STORM DRAIN (PVC SDR 35) 540 LF $48.30   $26,082.00    
  45 8" STORM DRAIN (PVC SDR 35) 20 LF $54.00   $1,080.00    
  46 8" STORM DRAIN FORCE MAIN (PVC C900) 10 LF $108.00   $1,080.00    
  47 12" STORM DRAIN (RCP CLASS III) 330 LF $70.00   $23,100.00    
  48 15" STORM DRAIN (RCP CLASS III) 800 LF $80.50   $64,400.00    
  49 STORM DRAIN SLOT DRAIN 50 LF $54.00   $2,700.00    
  50 STORM DRAIN TRENCH DRAIN 10 LF $54.00   $540.00    
  51 STORM DRAIN CLEANOUT 8 EA $537.00   $4,296.00    
  52 STORM DRAIN MANHOLE 8 EA $6,440.00   $51,520.00    
  53 STORM DRAIN FORCE MAIN JUNCTION BOX 1 EA $4,294.00   $4,294.00    
  54 STORM DRAIN LIFT STATION AND VALVE BOX 1 LS $480,000.00   $480,000.00    
  55 STORM DRAIN NUTRIENT SEPERATING BAFFLE BOX 1 EA $364,000.00   $364,000.00    
  56 STORM DRAIN AREA DRAIN 9 EA $644.00   $5,796.00    
  57 STORM DRAIN DROP INLET (12" X 12") 1 EA $3,220.00   $3,220.00    
  58 STORM DRAIN OVERFLOW DROP INLET (18" X 18") 1 EA $4,294.00   $4,294.00    
  59 STORM DRAIN CURB INLET (TYPE A) 4 EA $5,904.00   $23,616.00    
  60 STORM DRAIN CURB INLET (TYPE D) 1 EA $5,370.00   $5,370.00    
  61 15" BACKWATER VALVE 1 EA $3,800.00   $3,800.00    
  62 CONNECT TO EXISTING STORM DRAIN 1 EA $1,000.00   $1,000.00    
  63 EARTHWORK (EXCAVATION) 1,400 CY $26.80   $37,520.00    
  64 1-1/2" CHECK VALVE 1 EA $429.00   $429.00    
  65 2" CHECK VALVE 1 EA $429.00   $429.00    
  66 2-1/2" GATE VALVE 1 EA $483.00   $483.00    
  67 6" GATE VALVE 3 EA $1,074.00   $3,222.00    
  68 ADJUST WATER VALVE TO GRADE 3 EA $322.00   $966.00    
  69 ADJUST GAS VALVE TO GRADE 2 EA $322.00   $644.00    
  70 ADJUST MONITORING WELL TO GRADE 3 EA $322.00   $966.00    
  71 SET STREET MONUMENT 2 EA $600.00   $1,200.00    
  72 ROADSIDE SIGNS 7 EA $750.00   $5,250.00    
  73 STRIPING 1 LS $26,070.00   $26,070.00    
  74 TRAFFIC SIGNAL MODIFICATIONS AT MISSION BLVD AND C STREET 1 LS $102,000.00   $102,000.00    
  75 TRAFFIC SIGNAL MODIFICATIONS AT C STREET AND WATKINS STREET 1 LS $141,000.00   $141,000.00    
  76 INSTALL BUS SHELTER 1 EA $10,000.00   $10,000.00    
  77 WATER POLLUTION CONTROL 1 LS $48,000.00   $48,000.00    
  78 CONTRACTOR TEMPORARY TRAFFIC CONTROL 1 LS $13,000.00   $13,000.00    
  79 CLEARING AND GRUBBING 1 LS $38,000.00   $38,000.00    
  80 SOIL PREP AND FINISH GRADING 35,200 SF $0.60   $21,120.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Collins Electric
Stockton, CA 
Electrical $5,700,000.00 9.72% 115427 -   
  CLS Constructors
21935 Van Buren st Unit B-7
Grand Terrace, CA  92313 
Concrete (Bldg & Site) $4,947,620.00 8.44% 980071 -   
  Control Air Conditioning
5200 E La Palma Avenue
Anaheim, CA  92807 
HVAC Systems $3,609,000.00 6.15% 730186 -   
  Concord Ironworks, Inc.
1501 Loveridge Road Box 15
Pittsburg, CA  94565 
Structural/Misc Steel $3,370,915.00 5.75% 425897 -   
  Alcal Specialty Contracting
946 N Market Blvd
Sacramento, CA  95834 
Glazed Railings $295,000 Glass & Glazing $2,192,000 Translucent Glazing $450,000 $2,937,000.00 5.01% 815286 -   
  HARRISON DRYWALL INC.
850 S VAN NESS AVE
SAN FRANCISCO, CA  94107 
Metal studs & gypsum board $2,440,000.00 4.16% 620446 -   
  T3, Inc.
42307 Osgood Road
Suite F
Fremont, CA  94539 
Acoustical $2,258,121.00 3.85% 805816 -   
  Cleveland Marble
Orange, CA 
TerraCotta Rain Screen $1,970,346.00 3.36% 856767 -   
  Novum Structures
2 Union Square
Suite 210
Union City, CA  94587 
Glaze Cable Wall $1,100,000.00 1.87% 888637 -   
  WoodCraft Company
6700 GateWay Park Dr
Suite #4
San Diego, CA  92154 
Architectural woodwork $974,724.00 1.66% 940315 -   
  Gerdau Reinforcing Steel
San Diego, CA 
Rebar $944,348.00 1.61% 974202 -   
  Green Growth
Pleasanton, CA 
Landscape & irrigation $852,108.00 1.45% 662718 -   
  Ray L Hellwig Mechanical
Santa Clarita, CA 
Plumbing $849,880.00 1.45% 616780 -   
  European Paving Designs
San Jose, CA 
Permeable Pavers $306,902 Mortared Pavers $503,424 $810,326.00 1.38% 445163 -   
  Kingdom Pipelines
5700 Mission St
San Francisco, CA  94112 
Earthwork $277,350 Site Utilities $531,470 $808,820.00 1.38% 767686 -   
  Robert Boeger Plastering, Inc.
PO Box 495
Applegate, CA  95703 
EIFS & Plaster $530,000.00 0.9% 319451 -   
  R-Bros Painting
San Jose, CA 
Waterproofing $389,108.00 0.66% 472978 -   
  Linden Steel & Construction
Manteca, CA 
Metal Deck $352,900.00 0.6% 846699 -   
  CAMPANELLA CORPORATION
HAYWARD, CA 
Demo $346,900.00 0.59% 750648 -   
  Water-proofing Associates
975 Terra Bella Ave
Mountain View, CA  94043 
Roofing $338,499.00 0.57% 649862 -   
  Anderson carpet
1000 West Grand Ave
Oakland, CA  94607 
Flooring $297,166.00 0.5% 242102 -   
  Project Contractor, Inc.
South San Francisco, CA 
Fire sprinklers $237,500.00 0.4% 884221 -   
  Accurate Firestop
Hayward, CA 
Insulation $228,060.00 0.38% 710044 -   
  Otis Elevator
North Highlands, CA 
Elevators $195,750.00 0.33% 7031 -   
  American Fireproofing
Crown Point, IN 
Fireproofing $154,550.00 0.26% 1005033 -   
  Ross McDonald
1154 Stealth St
Livermore, CA  94551 
Library stacks $38,970.00 0.06% 314333 -