Bid Results

SHOULDER IMPROVEMENTS ON BACKUS ROAD FROM TEHACHAPI WILLOW SPRINGS ROAD TO STATE ROUTE 14

18165/3000-RC00027 


 
Show Bid Items
Show Listed Subcontractors
  go

General Contractor:  Bowman Asphalt
3351 Fairhaven Drive
Bakersfield, CA  93308 
  Bidder Status: Valid
 
Total Bid Amount:  $1,597,392.00 * marks an allowance.
  Bid List Name   Bid List Total    
  Shoulder improvements on Backus Rd from Tehachapi Willow Springs Rd to SR 14 $1,597,392.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 TEMPORARY TRAFFIC CONTROL 1 LS $166,600.50   $166,600.50    
  2 STORM WATER POLLUTION PREVENTION PLAN 1 LS $5,000.00   $5,000.00    
  3 REMOVE TRAFFIC STRIPE AND PAVEMENT MARKING 80 SQFT $32.75   $2,620.00    
  4 RELOCATE OBJECT MARKER 5 EA $500.00   $2,500.00    
  5 RELOCATE ROADSIDE SIGN – ONE POST 3 EA $500.00   $1,500.00    
  6 COLD PLANE ASPHALT CONCRETE PAVEMENT 79,800 LF $0.70   $55,860.00    
  7 CLEARING AND GRUBBING 1 LS $8,558.00   $8,558.00    
  8 DEVELOP WATER SUPPLY 1 LS $5,000.00   $5,000.00    
  9 ROADWAY EXCAVATION (F) 3,290 CY $50.00   $164,500.00    
  10 IMPORTED BORROW (F) 4,190 CY $56.00   $234,640.00    
  11 FINISHING ROADWAY 1 LS $5,000.00   $5,000.00    
  12 HOT MIX ASPHALT (TYPE A) 9,760 TN $83.00   $810,080.00    
  13 THERMOPLASTIC PAVEMENT MARKING 80 SQFT $32.75   $2,620.00    
  14 PAINT TRAFFIC STRIPE (2-COAT) 80,030 LF $0.45   $36,013.50    
  15 MOBILIZATION 1 LS $96,900.00   $96,900.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Austin Enterprise
13421 Snow Rd
Bakersfield, CA  93314 
CAS  -   
  Force Traffic Control, Inc.
PO Box 1107
Exeter, CA  93221 
Traffic control  -   
  Central Valley Striping
1100 N Gale Hill Avenue
Lindsay, CA  93247 
Remove traffic stripe, thermoplastic pavement markings, paint traffic stripe, mobilization  -   

General Contractor:  R.C. Becker and Son, Inc.
28355 Kelly Johnson Parkway
Santa Clarita, CA  91355 
  Bidder Status: Valid
 
Total Bid Amount:  $1,610,856.10 * marks an allowance.
  Bid List Name   Bid List Total    
  Shoulder improvements on Backus Rd from Tehachapi Willow Springs Rd to SR 14 $1,610,856.10  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 TEMPORARY TRAFFIC CONTROL 1 LS $46,496.05   $46,496.05    
  2 STORM WATER POLLUTION PREVENTION PLAN 1 LS $11,687.30   $11,687.30    
  3 REMOVE TRAFFIC STRIPE AND PAVEMENT MARKING 80 SQFT $92.00   $7,360.00    
  4 RELOCATE OBJECT MARKER 5 EA $115.00   $575.00    
  5 RELOCATE ROADSIDE SIGN – ONE POST 3 EA $212.75   $638.25    
  6 COLD PLANE ASPHALT CONCRETE PAVEMENT 79,800 LF $1.12   $89,376.00    
  7 CLEARING AND GRUBBING 1 LS $6,000.40   $6,000.40    
  8 DEVELOP WATER SUPPLY 1 LS $20,625.00   $20,625.00    
  9 ROADWAY EXCAVATION (F) 3,290 CY $61.74   $203,124.60    
  10 IMPORTED BORROW (F) 4,190 CY $22.33   $93,562.70    
  11 FINISHING ROADWAY 1 LS $134,465.40   $134,465.40    
  12 HOT MIX ASPHALT (TYPE A) 9,760 TN $96.24   $939,302.40    
  13 THERMOPLASTIC PAVEMENT MARKING 80 SQFT $11.50   $920.00    
  14 PAINT TRAFFIC STRIPE (2-COAT) 80,030 LF $0.40   $32,012.00    
  15 MOBILIZATION 1 LS $24,711.00   $24,711.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Interstate Striping & Signs, Inc.
1496 E Avenida De Los Arboles
Thousand Oaks, CA  91360 
Remove traffic stripe, relocate object marker, relocate roadside sign, thermoplastic pavement markings, and paint traffic stripe.  -   

General Contractor:  Granite Construction Company
3000 James Road
Bakersfield, CA  93308 
  Bidder Status: Valid
 
Total Bid Amount:  $1,824,885.00 * marks an allowance.
  Bid List Name   Bid List Total    
  Shoulder improvements on Backus Rd from Tehachapi Willow Springs Rd to SR 14 $1,824,885.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 TEMPORARY TRAFFIC CONTROL 1 LS $150,000.00   $150,000.00    
  2 STORM WATER POLLUTION PREVENTION PLAN 1 LS $15,000.00   $15,000.00    
  3 REMOVE TRAFFIC STRIPE AND PAVEMENT MARKING 80 SQFT $32.00   $2,560.00    
  4 RELOCATE OBJECT MARKER 5 EA $300.00   $1,500.00    
  5 RELOCATE ROADSIDE SIGN – ONE POST 3 EA $500.00   $1,500.00    
  6 COLD PLANE ASPHALT CONCRETE PAVEMENT 79,800 LF $1.25   $99,750.00    
  7 CLEARING AND GRUBBING 1 LS $25,000.00   $25,000.00    
  8 DEVELOP WATER SUPPLY 1 LS $15,000.00   $15,000.00    
  9 ROADWAY EXCAVATION (F) 3,290 CY $92.00   $302,680.00    
  10 IMPORTED BORROW (F) 4,190 CY $50.00   $209,500.00    
  11 FINISHING ROADWAY 1 LS $2,500.00   $2,500.00    
  12 HOT MIX ASPHALT (TYPE A) 9,760 TN $80.00   $780,800.00    
  13 THERMOPLASTIC PAVEMENT MARKING 80 SQFT $51.00   $4,080.00    
  14 PAINT TRAFFIC STRIPE (2-COAT) 80,030 LF $0.50   $40,015.00    
  15 MOBILIZATION 1 LS $175,000.00   $175,000.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Pavement Recycling Systems
10240 San Sevaine Way
Jurupa Valley, CA  91752 
operated milling machine for coldplane  -   
  Sterndahl
11861 Branford St
Sun Valley, CA  91352 
Traffic control, remove traffic stripe, relocate roadside sign, paint traffic stripe, and mobilization  -   
  Force Traffic Control, Inc.
PO Box 1107
Exeter, CA  93221 
Traffic control  -