FLOOD REPAIR ON CALIENTE CREEK ROAD AND CALIENTE BODFISH ROAD

18101/3000-RC00070 


 
Show Bid Items
Show Listed Subcontractors
  go

General Contractor:  Advanced Chemical Transport, Inc.
2655 Camino del Rio North Suite 100
San Diego, CA  92108 
  Bidder Status: Valid
 
Total Bid Amount:  $714,206.00 * marks an allowance.
  Bid List Name   Bid List Total    
  FLOOD REPAIR ON CALIENTE CREEK ROAD AND CALIENTE BODFISH ROAD $714,206.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 LEAD COMPLIANCE PLAN 1 LS $3,570.00   $3,570.00    
  2 TEMPORARY TRAFFIC CONTROL 1 LS $60,700.00   $60,700.00    
  3 PREPARE WATER POLLUTION CONTROL PROGRAM 1 LS $3,570.00   $3,570.00    
  4 CLEARING AND GRUBBING 1 LS $5,365.00   $5,365.00    
  5 DEVELOP WATER SUPPLY 1 LS $3,570.00   $3,570.00    
  6 ROADWAY EXCAVATION (F) 490 CY $570.00   $279,300.00    
  7 FINISHING ROADWAY 1 LS $107,130.00   $107,130.00    
  8 CLASS 2 AGGREGATE BASE 285 CY $50.00   $14,250.00    
  9 HOT MIX ASPHALT (TYPE A) 400 TN $80.00   $32,000.00    
  10 REINFORCED CONCRETE PAVEMENT 25 CY $214.00   $5,350.00    
  11 CONCRETED-ROCK SLOPE PROTECTION (LIGHT, METHOD B) (F) 440 CY $24.00   $10,560.00    
  12 PAINT TRAFFIC STRIPE (2-COAT) 1,840 LF $3.00   $5,520.00    
  13 MOBILIZATION 1 LS $35,040.00   $35,040.00    
  14 REMOVE AND DISPOSE MUD/SILT (F) 520 CY $55.00   $28,600.00    
  15 REMOVE CONCRETED-ROCK SLOPE PROTECTION (F) 440 CY $16.00   $7,040.00    
  16 DEWATERING 1 LS $10,700.00   $10,700.00    
  18 N/A LEAD COMPLIANCE PLAN 1 LS $3,570.00   $3,570.00    
  19 TEMPORARY TRAFFIC CONTROL 1 LS $14,500.00   $14,500.00    
  20 N/A PREPARE WATER POLLUTION CONTROL PROGRAM 1 LS $3,570.00   $3,570.00    
  21 N/A CLEARING AND GRUBBING 1 LS $1,800.00   $1,800.00    
  22 N/A DEVELOP WATER SUPPLY 1 LS $3,570.00   $3,570.00    
  23 N/A ROADWAY EXCAVATION (F) 25 CY $571.00   $14,275.00    
  24 N/A FINISHING ROADWAY 1 LS $7,700.00   $7,700.00    
  25 N/A CLASS 2 AGGREGATE BASE 15 CY $57.00   $855.00    
  26 N/A HOT MIX ASPHALT (TYPE A) 25 TN $86.00   $2,150.00    
  27 N/A PAINT TRAFFIC STRIPE (2-COAT) 130 LF $27.00   $3,510.00    
  28 N/A MOBILIZATION 1 LS $35,041.00   $35,041.00    
  17 N/A REMOVE YELLOW TRAFFIC STRIPE AND PAVEMENT MARKING (HAZARDOUS WASTE) 950 SQFT $12.00   $11,400.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Advanced Concrete
Reinforced Concrete Pavement, Concreted-Rock Slope protection  -   
  Safety Network
2361 N Larkin Ave
Fresno, CA  93727 
Traffic Control  -   
  South Valley Contractors
Demo  -   

General Contractor:  Bowman Asphalt
3351 Fairhaven Drive
Bakersfield, CA  93308 
  Bidder Status: Valid
 
Total Bid Amount:  $794,865.00 * marks an allowance.
  Bid List Name   Bid List Total    
  FLOOD REPAIR ON CALIENTE CREEK ROAD AND CALIENTE BODFISH ROAD $794,865.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 LEAD COMPLIANCE PLAN 1 LS $1,400.00   $1,400.00    
  2 TEMPORARY TRAFFIC CONTROL 1 LS $60,000.00   $60,000.00    
  3 PREPARE WATER POLLUTION CONTROL PROGRAM 1 LS $5,000.00   $5,000.00    
  4 CLEARING AND GRUBBING 1 LS $1,000.00   $1,000.00    
  5 DEVELOP WATER SUPPLY 1 LS $5,000.00   $5,000.00    
  6 ROADWAY EXCAVATION (F) 490 CY $223.00   $109,270.00    
  7 FINISHING ROADWAY 1 LS $7,000.00   $7,000.00    
  8 CLASS 2 AGGREGATE BASE 285 CY $240.00   $68,400.00    
  9 HOT MIX ASPHALT (TYPE A) 400 TN $220.00   $88,000.00    
  10 REINFORCED CONCRETE PAVEMENT 25 CY $1,030.00   $25,750.00    
  11 CONCRETED-ROCK SLOPE PROTECTION (LIGHT, METHOD B) (F) 440 CY $381.00   $167,640.00    
  12 PAINT TRAFFIC STRIPE (2-COAT) 1,840 LF $4.50   $8,280.00    
  13 MOBILIZATION 1 LS $70,000.00   $70,000.00    
  14 REMOVE AND DISPOSE MUD/SILT (F) 520 CY $80.00   $41,600.00    
  15 REMOVE CONCRETED-ROCK SLOPE PROTECTION (F) 440 CY $110.00   $48,400.00    
  16 DEWATERING 1 LS $61,900.00   $61,900.00    
  18 N/A LEAD COMPLIANCE PLAN 1 LS $100.00   $100.00    
  19 TEMPORARY TRAFFIC CONTROL 1 LS $1,400.00   $1,400.00    
  20 N/A PREPARE WATER POLLUTION CONTROL PROGRAM 1 LS $100.00   $100.00    
  21 N/A CLEARING AND GRUBBING 1 LS $100.00   $100.00    
  22 N/A DEVELOP WATER SUPPLY 1 LS $100.00   $100.00    
  23 N/A ROADWAY EXCAVATION (F) 25 CY $180.00   $4,500.00    
  24 N/A FINISHING ROADWAY 1 LS $500.00   $500.00    
  25 N/A CLASS 2 AGGREGATE BASE 15 CY $240.00   $3,600.00    
  26 N/A HOT MIX ASPHALT (TYPE A) 25 TN $220.00   $5,500.00    
  27 N/A PAINT TRAFFIC STRIPE (2-COAT) 130 LF $4.50   $585.00    
  28 N/A MOBILIZATION 1 LS $1,000.00   $1,000.00    
  17 N/A REMOVE YELLOW TRAFFIC STRIPE AND PAVEMENT MARKING (HAZARDOUS WASTE) 950 SQFT $9.20   $8,740.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Chrisp Company
1001 Stokes Ave
Stockton, CA  95215 
Lead compliance plan, Striping, Mobilization  -   

General Contractor:  Griffith Company
1128 Carrier Parkway Avenue
Bakersfield, CA  93308 
  Bidder Status: Valid
 
Total Bid Amount:  $911,145.00 * marks an allowance.
  Bid List Name   Bid List Total    
  FLOOD REPAIR ON CALIENTE CREEK ROAD AND CALIENTE BODFISH ROAD $911,145.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 LEAD COMPLIANCE PLAN 1 LS $1,500.00   $1,500.00    
  2 TEMPORARY TRAFFIC CONTROL 1 LS $37,415.00   $37,415.00    
  3 PREPARE WATER POLLUTION CONTROL PROGRAM 1 LS $3,100.00   $3,100.00    
  4 CLEARING AND GRUBBING 1 LS $1,500.00   $1,500.00    
  5 DEVELOP WATER SUPPLY 1 LS $1,200.00   $1,200.00    
  6 ROADWAY EXCAVATION (F) 490 CY $280.00   $137,200.00    
  7 FINISHING ROADWAY 1 LS $2,500.00   $2,500.00    
  8 CLASS 2 AGGREGATE BASE 285 CY $500.00   $142,500.00    
  9 HOT MIX ASPHALT (TYPE A) 400 TN $480.00   $192,000.00    
  10 REINFORCED CONCRETE PAVEMENT 25 CY $605.00   $15,125.00    
  11 CONCRETED-ROCK SLOPE PROTECTION (LIGHT, METHOD B) (F) 440 CY $310.00   $136,400.00    
  12 PAINT TRAFFIC STRIPE (2-COAT) 1,840 LF $4.50   $8,280.00    
  13 MOBILIZATION 1 LS $30,000.00   $30,000.00    
  14 REMOVE AND DISPOSE MUD/SILT (F) 520 CY $85.00   $44,200.00    
  15 REMOVE CONCRETED-ROCK SLOPE PROTECTION (F) 440 CY $85.00   $37,400.00    
  16 DEWATERING 1 LS $7,500.00   $7,500.00    
  18 N/A LEAD COMPLIANCE PLAN 1 LS $1,500.00   $1,500.00    
  19 TEMPORARY TRAFFIC CONTROL 1 LS $37,415.00   $37,415.00    
  20 N/A PREPARE WATER POLLUTION CONTROL PROGRAM 1 LS $3,100.00   $3,100.00    
  21 N/A CLEARING AND GRUBBING 1 LS $1,500.00   $1,500.00    
  22 N/A DEVELOP WATER SUPPLY 1 LS $1,200.00   $1,200.00    
  23 N/A ROADWAY EXCAVATION (F) 25 CY $280.00   $7,000.00    
  24 N/A FINISHING ROADWAY 1 LS $2,500.00   $2,500.00    
  25 N/A CLASS 2 AGGREGATE BASE 15 CY $500.00   $7,500.00    
  26 N/A HOT MIX ASPHALT (TYPE A) 25 TN $480.00   $12,000.00    
  27 N/A PAINT TRAFFIC STRIPE (2-COAT) 130 LF $4.50   $585.00    
  28 N/A MOBILIZATION 1 LS $30,000.00   $30,000.00    
  17 N/A REMOVE YELLOW TRAFFIC STRIPE AND PAVEMENT MARKING (HAZARDOUS WASTE) 950 SQFT $9.50   $9,025.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  Austin Enterprise
PO Box 81926
Bakersfield, CA  93380 
CAS  -   
  Chrisp Company
1001 Stokes Ave
Stockton, CA  95215 
Lead compliance plan, stripe, pavement marking  -