Bid Results

PHASE 2A MODULE 4 LINER AT BAKERSFIELD METROPOLITAN AT (BENA) SANITARY LANDFILL

18171/8999-BEN-10/11 


 
Show Bid Items
Show Listed Subcontractors
  go

General Contractor:  Innovative Construction Solutions
575 Anton Blvd Suite 850
Costa Mesa, CA  92626 
  Bidder Status: Valid
 
Total Bid Amount:  $11,212,462.00 * marks an allowance.
  Bid List Name   Bid List Total    
  Phase 2A, Module 4 liner at BENA $11,212,462.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 MOBILIZATION AND DEMOBILIZATION 1 LS $233,000.00   $233,000.00    
  2 SURVEYING 1 LS $50,000.00   $50,000.00    
  3 TEMPORARY CONTROL PLANS 1 LS $10,000.00   $10,000.00    
  4 TEMPORARY WATER SERVICE 1 LS $60,000.00   $60,000.00    
  5 EXCAVATION AND PLACEMENT IN STOCKPILE A(A-1 & A-2)(F) 168,900 CY $2.70   $456,030.00    
  6 EXCAVATION AND PLACEMENT IN STOCKPILE B (F) 112,600 CY $2.70   $304,020.00    
  7 EXCAVATION AND PLACEMENT IN STOCKPILE C (F) 765,800 CY $2.70   $2,067,660.00    
  8 EXCAVATION AND PLACEMENT IN STOCKPILE D (F) 128,800 CY $2.70   $347,760.00    
  9 EXCAVATION AND PLACEMENT IN STOCKPILE G (F) 921,600 CY $2.60   $2,396,160.00    
  10 EXCAVATION AND PLACEMENT AS ENGINEERED FILL (F) 23,500 CY $4.00   $94,000.00    
  11 LINER TERMINATION BERM AND ANCHOR TRENCH 2,900 LF $18.00   $52,200.00    
  12 FLOOR LINER TERMINATION BERM AND ANCHOR TRENCH 400 LF $23.00   $9,200.00    
  13 SIDE SLOP LINER TERMINATION ANCHOR TRENCH 300 LF $30.00   $9,000.00    
  14 BENCH ANCHOR TRENCH 1,900 LF $27.00   $51,300.00    
  15 SIDE SLOP SUBGRADE PREPARATION 693,800 SF $0.10   $69,380.00    
  16 CONSTRCTION IN PLACE ENGINEERED SOIL FOUNDATION LAYER 7,500 CY $7.00   $52,500.00    
  17 HAUL AND PLACE ENGINEERED SOIL FOUNDATION LAYER 3,500 CY $7.50   $26,250.00    
  18 60-MIL SINGLE-TEXTURED BLACK AND WHITE HDPE 1,324,200 SF $0.75   $993,150.00    
  19 40-MIL DOUBLE-TEXTURED HDPE GEOMEMBRANCE 1,325,200 SF $0.65   $861,380.00    
  20 N/A GEOCOMPOSITE 610,400 SF $0.80   $488,320.00    
  21 GEOSYNTHETIC CLAY LINER 1,327,500 SF $0.80   $1,062,000.00    
  22 PREPARE STORM WATER POLLUTION PREVENTION PLAN 1 LS $63,000.00   $63,000.00    
  23 FILTER GEOTEXTILE 55,700 SF $0.20   $11,140.00    
  24 DRAINAGE GRAVEL 500 CY $150.00   $75,000.00    
  25 OPERATIONS LAYER (F) 44,900 CY $13.00   $583,700.00    
  26 4'' HDPE PIPE 1,600 LF $25.00   $40,000.00    
  27 24'' CMP CULVERT 3,800 LF $31.00   $117,800.00    
  28 36'' CMP CULVERT 484 LF $195.00   $94,380.00    
  29 EROSION CONROL MAT 95 LF $300.00   $28,500.00    
  30 HYDROSEEDING 67,600 SF $1.57   $106,132.00    
  31 ROADWAY EDGE DELINEATORS 51 AC $2,000.00   $102,000.00    
  32 TYPE II BARRICADES 3,600 LF $5.00   $18,000.00    
  33 DRAINAGE STRUCTURE PROTECTION BOLLARDS 1 LS $11,000.00   $11,000.00    
  34 GRAVEL STRUCTURE PROTECTION BOLLARDS 1 LS $16,000.00   $16,000.00    
  35 GRAVEL BAG CHECK DAMS 1 LS $102,500.00   $102,500.00    
  36 FIBER ROLLS 1 LS $133,000.00   $133,000.00    
  37 GEOELECTRIC LEAK LOCATION SURVEY SUPPORT 1 LS $17,000.00   $17,000.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  D & E Construction
14175 Avenue 344
Visalia, CA  93292 
Liner Installation  -   
  Superior Gunite
12306 Van Nuys Blvd
Lake View Terrace, CA  91342-6049 
shotcrete  -   
  Marina Landscaping
Erosion control/ Hydroseeding  -   

General Contractor:  Sukut Construction
4010 W Chandler Avenue
Santa Ana, CA  92704 
  Bidder Status: Valid
 
Total Bid Amount:  $11,428,612.50 * marks an allowance.
  Bid List Name   Bid List Total    
  Phase 2A, Module 4 liner at BENA $11,428,612.50  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 MOBILIZATION AND DEMOBILIZATION 1 LS $999,999.50   $999,999.50    
  2 SURVEYING 1 LS $117,000.00   $117,000.00    
  3 TEMPORARY CONTROL PLANS 1 LS $26,000.00   $26,000.00    
  4 TEMPORARY WATER SERVICE 1 LS $78,000.00   $78,000.00    
  5 EXCAVATION AND PLACEMENT IN STOCKPILE A(A-1 & A-2)(F) 168,900 CY $2.10   $354,690.00    
  6 EXCAVATION AND PLACEMENT IN STOCKPILE B (F) 112,600 CY $1.88   $211,688.00    
  7 EXCAVATION AND PLACEMENT IN STOCKPILE C (F) 765,800 CY $2.20   $1,684,760.00    
  8 EXCAVATION AND PLACEMENT IN STOCKPILE D (F) 128,800 CY $3.55   $457,240.00    
  9 EXCAVATION AND PLACEMENT IN STOCKPILE G (F) 921,600 CY $2.65   $2,442,240.00    
  10 EXCAVATION AND PLACEMENT AS ENGINEERED FILL (F) 23,500 CY $3.40   $79,900.00    
  11 LINER TERMINATION BERM AND ANCHOR TRENCH 2,900 LF $23.00   $66,700.00    
  12 FLOOR LINER TERMINATION BERM AND ANCHOR TRENCH 400 LF $46.00   $18,400.00    
  13 SIDE SLOP LINER TERMINATION ANCHOR TRENCH 300 LF $52.00   $15,600.00    
  14 BENCH ANCHOR TRENCH 1,900 LF $33.00   $62,700.00    
  15 SIDE SLOP SUBGRADE PREPARATION 693,800 SF $0.16   $111,008.00    
  16 CONSTRCTION IN PLACE ENGINEERED SOIL FOUNDATION LAYER 7,500 CY $3.25   $24,375.00    
  17 HAUL AND PLACE ENGINEERED SOIL FOUNDATION LAYER 3,500 CY $29.00   $101,500.00    
  18 60-MIL SINGLE-TEXTURED BLACK AND WHITE HDPE 1,324,200 SF $0.74   $979,908.00    
  19 40-MIL DOUBLE-TEXTURED HDPE GEOMEMBRANCE 1,325,200 SF $0.60   $795,120.00    
  20 N/A GEOCOMPOSITE 610,400 SF $0.83   $506,632.00    
  21 GEOSYNTHETIC CLAY LINER 1,327,500 SF $0.79   $1,048,725.00    
  22 PREPARE STORM WATER POLLUTION PREVENTION PLAN 1 LS $50,000.00   $50,000.00    
  23 FILTER GEOTEXTILE 55,700 SF $0.22   $12,254.00    
  24 DRAINAGE GRAVEL 500 CY $74.00   $37,000.00    
  25 OPERATIONS LAYER (F) 44,900 CY $7.65   $343,485.00    
  26 4'' HDPE PIPE 1,600 LF $20.00   $32,000.00    
  27 24'' CMP CULVERT 3,800 LF $13.70   $52,060.00    
  28 36'' CMP CULVERT 484 LF $280.00   $135,520.00    
  29 EROSION CONROL MAT 95 LF $375.00   $35,625.00    
  30 HYDROSEEDING 67,600 SF $3.18   $214,968.00    
  31 ROADWAY EDGE DELINEATORS 51 AC $2,100.00   $107,100.00    
  32 TYPE II BARRICADES 3,600 LF $3.80   $13,680.00    
  33 DRAINAGE STRUCTURE PROTECTION BOLLARDS 1 LS $235.00   $235.00    
  34 GRAVEL STRUCTURE PROTECTION BOLLARDS 1 LS $37,000.00   $37,000.00    
  35 GRAVEL BAG CHECK DAMS 1 LS $4,500.00   $4,500.00    
  36 FIBER ROLLS 1 LS $138,000.00   $138,000.00    
  37 GEOELECTRIC LEAK LOCATION SURVEY SUPPORT 1 LS $33,000.00   $33,000.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  D & E Construction
14175 Avenue 344
Visalia, CA  93292 
Liner  -   
  Marina Landscaping
Erosion control  -   
  Southwest V-Ditch
3625 Placentia Lane
Riverside, CA  92501 
Concrete  -   

General Contractor:  Wood Bros Inc
PO Box 216
Lemoore, CA  93245 
  Bidder Status: Valid
 
Total Bid Amount:  $11,794,638.00 * marks an allowance.
  Bid List Name   Bid List Total    
  Phase 2A, Module 4 liner at BENA $11,794,638.00  
  Item #   Item Code   Item Description   Estimated
Quantity
Unit of
Measure
Unit Price   Item Total    
  1 MOBILIZATION AND DEMOBILIZATION 1 LS $680,624.00   $680,624.00    
  2 SURVEYING 1 LS $89,225.00   $89,225.00    
  3 TEMPORARY CONTROL PLANS 1 LS $107,950.00   $107,950.00    
  4 TEMPORARY WATER SERVICE 1 LS $39,100.00   $39,100.00    
  5 EXCAVATION AND PLACEMENT IN STOCKPILE A(A-1 & A-2)(F) 168,900 CY $3.46   $584,394.00    
  6 EXCAVATION AND PLACEMENT IN STOCKPILE B (F) 112,600 CY $3.62   $407,612.00    
  7 EXCAVATION AND PLACEMENT IN STOCKPILE C (F) 765,800 CY $2.40   $1,837,920.00    
  8 EXCAVATION AND PLACEMENT IN STOCKPILE D (F) 128,800 CY $2.96   $381,248.00    
  9 EXCAVATION AND PLACEMENT IN STOCKPILE G (F) 921,600 CY $2.57   $2,368,512.00    
  10 EXCAVATION AND PLACEMENT AS ENGINEERED FILL (F) 23,500 CY $4.49   $105,515.00    
  11 LINER TERMINATION BERM AND ANCHOR TRENCH 2,900 LF $20.40   $59,160.00    
  12 FLOOR LINER TERMINATION BERM AND ANCHOR TRENCH 400 LF $41.33   $16,532.00    
  13 SIDE SLOP LINER TERMINATION ANCHOR TRENCH 300 LF $66.23   $19,869.00    
  14 BENCH ANCHOR TRENCH 1,900 LF $31.57   $59,983.00    
  15 SIDE SLOP SUBGRADE PREPARATION 693,800 SF $0.24   $166,512.00    
  16 CONSTRCTION IN PLACE ENGINEERED SOIL FOUNDATION LAYER 7,500 CY $6.95   $52,125.00    
  17 HAUL AND PLACE ENGINEERED SOIL FOUNDATION LAYER 3,500 CY $6.35   $22,225.00    
  18 60-MIL SINGLE-TEXTURED BLACK AND WHITE HDPE 1,324,200 SF $0.77   $1,019,634.00    
  19 40-MIL DOUBLE-TEXTURED HDPE GEOMEMBRANCE 1,325,200 SF $0.63   $834,876.00    
  20 N/A GEOCOMPOSITE 610,400 SF $0.85   $518,840.00    
  21 GEOSYNTHETIC CLAY LINER 1,327,500 SF $0.82   $1,088,550.00    
  22 PREPARE STORM WATER POLLUTION PREVENTION PLAN 1 LS $13,398.00   $13,398.00    
  23 FILTER GEOTEXTILE 55,700 SF $0.15   $8,355.00    
  24 DRAINAGE GRAVEL 500 CY $133.00   $66,500.00    
  25 OPERATIONS LAYER (F) 44,900 CY $4.83   $216,867.00    
  26 4'' HDPE PIPE 1,600 LF $10.80   $17,280.00    
  27 24'' CMP CULVERT 3,800 LF $16.70   $63,460.00    
  28 36'' CMP CULVERT 484 LF $346.00   $167,464.00    
  29 EROSION CONROL MAT 95 LF $224.00   $21,280.00    
  30 HYDROSEEDING 67,600 SF $6.76   $456,976.00    
  31 ROADWAY EDGE DELINEATORS 51 AC $2,944.00   $150,144.00    
  32 TYPE II BARRICADES 3,600 LF $12.40   $44,640.00    
  33 DRAINAGE STRUCTURE PROTECTION BOLLARDS 1 LS $192.00   $192.00    
  34 GRAVEL STRUCTURE PROTECTION BOLLARDS 1 LS $34,500.00   $34,500.00    
  35 GRAVEL BAG CHECK DAMS 1 LS $23,000.00   $23,000.00    
  36 FIBER ROLLS 1 LS $43,856.00   $43,856.00    
  37 GEOELECTRIC LEAK LOCATION SURVEY SUPPORT 1 LS $6,320.00   $6,320.00    
  Listed Subcontractors   Description of Work   Listing Amount   Percent of Contract   License No - Expiration    
  D & E Construction
14175 Avenue 344
Visalia, CA  93292 
Liner system  -   
  Southwest V-Ditch
3625 Placentia Lane
Riverside, CA  92501 
Shotcrete  -   
  Shelbys Soil Erosion Control
Erosion Control  -